Project Description
Design scaffolding with a temporary roof used during the roof replacement to ensure the main area of the church wasn’t damaged by the elements. VMZinc Pigmento Green used to replace and imitate the original copper roof and appease planning. The VM Zinc was a CDP item A church pre-school uses the adjacent church hall, and their ongoing safe access and egress was important. 3M height to perimeter of the scaffolding was fitted in corrugated iron sheets to ensure security. High winds, given the location, tested the temporary roof with one storm causing minimum damage to the mono-flex sheeting.
We needed to be careful not to cause damage to the underside of the ceiling when insulating (PIR Insulation) etc which was tricky, but we did achieve no internal damage.